The Troubleshooter: Key Steps to a Stable Injection Molding Process

Garrett MacKenzie | Jul 17, 2023

In the fast-paced world of process engineering, process development is crucial to the success or failure of a plastic injection system. Solid processes must run at 100% efficiency with preferably zero — but no more than 1.5% — scrap to maintain plant profitability. This article will define many of the critical points that define process stability. It will also recommend methods to ensure that a process is both consistent and repeatable.

One of the most important stages of process development is setting up the mold and work area. It is important to develop a consistent, repeatable method that takes into account the steps, tools, and equipment used in every mold-to-mold changeover. Setting the mold the same way every time ensures that the process itself will be repeatable. Standardizing knockouts, retainer rings, water/ hydraulic fittings, and so forth helps to remove human error and inconsistency in the setup process.

Clamp and ejector setup are crucial to the process development stage. Low-pressure close must be set up to protect the mold from damage during mold close. Clamp speeds should be quick to ensure they are optimized, but not lunging in a manner that might put the mold in jeopardy. Ejectors should be as fast as possible without bottoming out, which could affect mold life.

The following is a list of critical parameters that, if set incorrectly, could cause inconsistencies in a process.

Once a process has been proven to be producing quality parts, the first stage of validation is to produce quality parts at 100% efficiency with 0 to 1.5% scrap for eight hours. Once this has been achieved, all setup data is then recorded. The second stage of validation occurs the next time the mold is set up to run. The initial set points from the previous run are used again. The press must start, only producing two to three scrap parts before quality parts are achieved. If this becomes truth, the press then must repeat the previous achievement of 100% efficiency with 0 to 1.5% scrap. Once this is accomplished, the process is fully validated. This is when historical data and process control limits are established.

Process development is a complex dynamic that requires meticulous focus. Solid process regimens require a strong approach to ensure that the process is consistent and achievable. Once process validation and process control limits have been established, it becomes easier to monitor a process and troubleshoot changes within the process scope.

Got a problem with this, that, or the other thing? You might find answers in some previous "Troubleshooter" columns:

How to Identify and Correct Shear-Related Splay Defects

The Role of Moisture in Injection Molding Splay Defects

Preventing Flash in Injection Molded Parts

How to Prevent Common Failure Modes in Injection Molding

Building a Validated Plastic Injection Molding Process

Fixing Color Defects in Injection Molded Parts

About the author

Garrett MacKenzie is the owner/editor of plastic411.com and a consultant/trainer in plastic injection molding. He has provided process-engineering expertise to many top companies, including Glock, Honda, Johnson Controls, and Rubbermaid. MacKenzie also owns Plastic411 Services, which provides maintenance and training support to Yanfeng Automotive Interior Systems, IAC, Flex-N-Gate, and other top automotive suppliers. He was inducted into the Plastic Pioneers Association (PPA) in 2019, where he serves on the Education Committee evaluating applications from college students seeking PPA scholarships. You can reach him via e-mail at [email protected].

More information about text formats

Check out our coverage of mind-blowing new plastics applications and more.

Shot sizeBarrel temperaturesHold and pack pressuresInjection speedsBack pressure settingsHot runner set pointsGot a problem with this, that, or the other thing? You might find answers in some previous "Troubleshooter" columns:About the author